Action plan for full power generation in Yadadri: TG Genco prepares with a target of 4,000 MW

Commercial production of the 5th unit in December.. Measures to strengthen the coal supply system. Hyderabad, Trinet News, November 17: TG Genco has initiated an action plan to achieve full-scale power generation of 4,000 MW at the Yadadri Thermal Power Station by the upcoming Rabi season.

nagendra18 November 2026, 5:56 AM10 viewstrinetnews.com
Action plan for full power generation in Yadadri: TG Genco prepares with a target of 4,000 MW

Commercial production of the fifth unit in December.. Measures to strengthen the coal supply system. Hyderabad, Trinet News, November 17: TG Genco has formulated an action plan to achieve full-scale power generation of 4,000 MW at the Yadadri Thermal Power Station by the upcoming Rabi season.

Four out of the five units, each with a capacity of 800 MW, are already in commercial production. The fifth unit, which was synchronized with the grid on October 20, targets to begin commercial production in December. The government has focused on resolving technical issues that arose in the coal handling system. Under the directives of Chief Minister Revanth Reddy and the guidance of Deputy Chief Minister Bhatti Vikramarka, a high-level BHEL-TG Genco team led by the Special Chief Secretary of the Energy Department inspected the plant and formulated a specific target-oriented plan to resolve the issues.

Officials stated that four coal supply lines have been restored, reaching a capacity to transport a total of 3,200 tonnes of coal at an average of 800 tonnes per hour in each line.

Multi-pronged arrangements for coal supply: To ensure uninterrupted coal supply to the plant, arrangements have been made to transport three to four railwayrakes of coal per day from the Naini mine belonging to Singareni. So far, 4.26 lakh metric tonnes of coal have been transported from this mine to Yadadri. Fuel supply agreements were concluded on November 4 to purchase another 4.6 lakh tonnes of coal from MCL and SECL companies under the Window-II auction method, and transportation from these companies has begun. For long-term requirements, the Standing Linkage Committee has approved the supply of 7.71 million tonnes of coal per year from MCL and ECL for two units of the plant. Officials stated that these arrangements will improve coal availability and help minimize disruptions in production.

Phased repairs from November 18: To improve the performance of the coal handling plant, restoration work on the first supply line will be undertaken from November 18 to 24. During this time, the remaining three units will be kept available, and a plan has been made to continue power generation of a total of 2,000 MW through four units. Depending on the requirement, generation will be limited to 1,800 MW in coordination with the State Load Despatch Center. Works will be carried out in departments such as conveyor belts, feeders, crushers, stackers, and reclaimers under the supervision of BHEL and TG Genco, with necessary spare parts kept ready. After repairs, BHEL must demonstrate the capacity to transport 2,500 tonnes of coal per hour on the first line. Subsequently, works will be undertaken in a phased manner on the remaining lines.

Peak production on November 11: According to details revealed by officials, TG Genco's power generation reached a record peak level of 6,088 MW for the first time on November 11, in which the share of the Yadadri plant was 2,754 MW. With the restoration of the coal supply system and the commercial production of the fifth unit, TG Genco is preparing to reach the 4,000 MW target during the Rabi season.

Also read

Arrest of Accused in Gold Necklace Theft Case

Arrest of Accused in Gold Necklace Theft Case

The accused in a gold necklace theft case was arrested after luring the victim to her home and stealing a three‑tola gold necklace; the suspect was taken into custody by Chilakalguda police and transferred to Secunderabad for judicial remand, trinet NEWS, November 24.

Read more →